CEX Technical Team Resolves Black E-Coating Quality Issues: ADC12 Aluminum Die-Cast Parts Reach 25,000 Units in Cumulative Deliveries

Last week, with the latest batch of six cartons sealed and shipped, CEX Casting’s cumulative deliveries of ADC12 aluminum die-cast SINK parts to the customer reached 25,000 units.

From the initial small-batch trial orders to ongoing repeat orders totaling tens of thousands of units, this milestone reflects the customer’s confidence in our ability to solve practical process challenges and maintain consistent delivery performance.

These SINK parts go through multiple manufacturing processes, including die casting, CNC machining, and black e-coating.

CNC Machined ADC12 SINK Parts and Six Cartons of SINK Parts After Packaging

In the early stages of the project, the surface treatment process presented a challenge.

Occasional defects appeared after black e-coating, affecting the final appearance and anti-corrosion performance.

To address this issue, the CEX technical team conducted an in-depth investigation into the surface treatment process.

After repeated verification, we found the root cause: the surface condition before e-coating was not ideal, resulting in unstable coating adhesion.

To resolve this, we officially added sandblasting as a key process in production.

 

To determine the appropriate mesh sizes and processing sequence, CEX conducted comparative tests on multiple approaches.

We finally established a two-stage process. First, 85-mesh abrasive is used for the initial blasting pass.

An air gun is then used to thoroughly remove residual coarse abrasive from the surfaces and gaps.

Next, finer 180-mesh abrasive is used for a second blasting pass to achieve a consistent and delicate sandy texture on the surface.

Although this process is time-consuming and labor-intensive, it is precisely this uncompromising attention to detail that provides an ideal foundation for e-coating adhesion and ensures the smooth finish and premium texture of the coated surface.

ADC12 SINK Parts After Sandblasting and Black E-Coating

For packaging, each product is individually wrapped in a bubble bag and then placed in a carton to reduce impact and friction during transportation, ensuring that the products arrive at the customer’s premises intact.

 

By introducing sandblasting into the surface treatment process, CEX Casting has bridged the critical gap between the as-cast part and e-coating, enabling us to continuously provide customers with products that meet both appearance and anti-corrosion performance standards.

Production of the new batch is currently progressing according to plan.